Facility |
GRP Madison Renewable Energy Facility |
County |
Madison County |
Cause of Order |
Discharge of wastewater without a permit; buffer zone between the Fire Pond and neighboring property does not meet criteria; failure to provide complete and accurate information and materials in NPDES permit application; site map was not updated to show all conveyances and inlets; discharge of standing air compressor blowdown contaminated compressor oil; Stormwater Pond is of insufficient size and capacity |
Requirements of Order |
Shall not discharge wastewater from Outfall 001 or 002 until NPDES wastewater permit has been issued; shall not resume operation of the evaporators in Fire Pond until permit is issued; maintain manifests of shipment and off-site disposal and/or treatment of all process wastewater; ensure that any remaining non-contaminated stormwater runoff is management properly; submit a written Management Plan and copies of all manifests or other records in its possession for the disposal of wastewater |
Settlement Amount |
$16,800.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
18‑Jun‑2020 |
Publication Date For Executed Order |
22‑Jun‑2020 |
File Attachments |
None
|