Enforcement Order EPD-WP-9125
Facility | McDuffie County |
---|---|
County | McDuffie County |
Cause of Order | Failed to timely complete or verify submittal of the GEOS filing to obtain General Permit coverage for construction activities; failed to ensure that their contractors properly install, implement, and maintain BMPs; failed to obtain a 7-day letter; contractors tracked vehicles and equipment across Perennial Stream 5 without a properly installed temporary stream crossing leading to a loss of sediment into State Water |
Requirements of Order | Require and ensure contractors immediately install and maintain BMPs according to the Site's ES&PCP |
Settlement Amount | $5,800.00 |
Legal Authority | Water Quality Control Act (including Surface Water Allocation) |
Date Executed | 8‑Sep‑2021 |
Publication Date For Executed Order | 13‑Sep‑2021 |