Enforcement Order EPD-WP-9157

Facility Hand Construction & Projects, LLC
County Grady County
Cause of Order Failed to implement BMPs resulting in a significant discharge of sediment into a water of the state; failed to identify a second outfall for the land disturbance; failed to sample stormwater discharges at the second outfall
Requirements of Order Have a certified Design Professional amend the ESPCP to include all outfall locations and additional sediment control BMPs; fully implement the amended ESPCP and all BMPs at the Site; remove the sediment that was discharged in the adjacent water of the state; collect a stormwater turbidity sample from each outfall during the next qualifying rainfall event and submit
Settlement Amount $5,000.00
Legal Authority Water Quality Control Act (including Surface Water Allocation)
Date Executed 19‑Nov‑2021
Publication Date For Executed Order 22‑Nov‑2021