Facility |
Northwest Georgia Paving Inc |
County |
Bartow County |
Cause of Order |
Installing a drainage structure within the 50 foot trout stream buffer without first obtaining a stream buffer variance; failing to design and indicate a 50 foot trout stream buffer on the ESPCP; failing to indicate storm water monitoring on the NOI; failing to indicate accurate state waters classification on the NOI; failing to design, install and/or maintain BMPs; failing to design the ESPCP and conduct storm water monitoring as required to achieve representative turbidity sampling; failing to temporarily stabilize all disturbed areas not worked within 14 days; failing to require the Design Professional to certify the ESPCP after any changes in construction, operation, and/or maintenance which had a significant effect on BMPs with a hydraulic component; failing to amend newly added BMP changes to the ESPCP within 7 calendar days; failing to document all incidences of noncompliance; failing to submit violation summary reports with 14 days of discovery |
Requirements of Order |
Amend the NOI to accurately reflect all conditions and construction schedules; contact the US ACE to determine if a permit is required for any portion of the site prior to proceeding with any applicable construction activities; bring the Site into full Permit compliance; existing drainage structure may remain in-situ at the Site if Respondent completes previous conditions |
Settlement Amount |
$6,459.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
16‑Dec‑2021 |
Publication Date For Executed Order |
20‑Dec‑2021 |
File Attachments |
None
|