Facility |
North Perimeter Contractors LLC |
County |
Fulton County |
Cause of Order |
Failure to conduct NTU monitoring during dredging restoration activities that resulted in sediment being pumped into waters of the State; failure to comply with the CAP required by EPD-WP-9063; failure to implement the ESPCP by failing to conduct permit required NTU sampling for pumped discharges; failure to comply with 2 NOVs that required ceasing all noncompliant discharges from the Site; failure to implement with the approved King and Queen Pond Restoration Work Plan and Restoration ESPCP for the dredging activities |
Requirements of Order |
Comply with Rules and pay penalty |
Settlement Amount |
$29,845.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
26‑Jul‑2022 |
Publication Date For Executed Order |
1‑Aug‑2022 |
File Attachments |
None
|