Enforcement Order EPD-WP-9678

Facility Silicon Ranch Corporation
County Toombs County
Cause of Order BMPs were not properly designed, installed, or maintained; multiple releases resulted in sediment deposition outside the Limits of Disturbance and into waters of the State due to improper design, installation, or maintenance of the BMPs; stormwater discharges exceeding the nephelometric turbidity unit have occurred due to improper design, installation, or maintenance of the BMPs; BMPs that have failed or are deficient were not repaired in accordance with the timeframes; the revised ESPCP was not implemented in accordance with the timeframe
Requirements of Order Provide a Corrective Action Plan for EPD review and approval; have the certified Design Professional conduct a 7 day inspection of any redesigned BMPs in each parcel and acquire the 7 day inspection letter
Settlement Amount $1,105,000.00
Legal Authority Water Quality Control Act (including Surface Water Allocation)
Date Executed 25‑Jul‑2025
Publication Date For Executed Order 28‑Jul‑2025