Facility |
1-75 construction project site (NH-75-1 {203})/Douglas; order issued to Douglas Asphalt Company |
County |
Lowndes County |
Cause of Order |
Violations of General NPDES Permit for Storm Water Discharges Associated with Construction Activity |
Requirements of Order |
Cease any additional encroachment into 25 foot stream buffer; initiate proper stabilization measures on all disturbed areas within the 25 ft stream buffer; properly install/maintain erosion and sedimentation control measures as specified in the Erosion, Sedimentation and Pollution Control Plan |
Settlement Amount |
$3,750.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
24‑May‑2005 |
Publication Date For Executed Order |
30‑May‑2005 |
File Attachments |
None
|