Facility |
Big Creek Water Reclamation Plant (WRP); Fulton County sewer system |
County |
Fulton County |
Cause of Order |
Discharge of nondisinfected effluent from Big Creek WRC; sewer system overflows |
Requirements of Order |
Develop Standard Operating Procedure for wastewater treatment spills; evaluate alternate power systems for treatment plants and pump stations ; submit schedule for implementing recommendations; conduct stream sampling |
Settlement Amount |
$26,000.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Publication Date For Proposed Order |
15‑Feb‑1999 |
Date Comment Period Closes |
17‑Mar‑1999 |
Date Executed |
30‑Mar‑1999 |
Publication Date For Executed Order |
5‑Apr‑1999 |
File Attachments |
None
|