Facility |
American Egg Products, Inc. |
County |
Pierce County |
Cause of Order |
Exceeded discharge limits in Permit for parameter BOD in June and August 2016 and TKN in April, May, June, July, October, November & December 2016; failed to ensure compliance w/ terms & conditions of Permit; violation of Permit for not maintaining facility in good working order; violation of Permit for not having a Certified Operator |
Requirements of Order |
w/in 90 days provide name and certification number of person in responsible charge of the daily operation of facility; w/in 60 days submit Corrective Action Plan (CAP); implement the approved CAP; submit a final progress report from professional engineer; |
Settlement Amount |
$2,000.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
11‑May‑2017 |
Publication Date For Executed Order |
15‑May‑2017 |
File Attachments |
None
|