Facility |
Serenbe Phase 3A Mado |
County |
Fulton County |
Cause of Order |
Failure to properly design, install and maintain BMPs; failure to obtain a warm water stream buffer variance; failure to conduct required inspections and reports; disturbed additional acreage beyond the limits of disturbance in accordance with the ESPCP and failed to pay additional fees associated w/ construction activity |
Requirements of Order |
w/in 30 days bring Facility into full Permit compliance; w/in 30 days pay all fees associated with this Site; w/in 30 days submit the Corrective Action Plan outlining restoration of 25 foot state buffer and timeline for completion. |
Settlement Amount |
$10,000.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
13‑Jun‑2017 |
Publication Date For Executed Order |
19‑Jun‑2017 |
File Attachments |
None
|