Enforcement Order EPD-WP-8294
Facility | Made in the Shade Campground |
---|---|
County | Burke County |
Cause of Order | Operate a Public Water System without first being issued a modified permit from the Division; failure to operate the Water System in accordance with the Rules, Regulations and Orders |
Requirements of Order | Immediately begin to comply w/ the Drinking Water Act, Drinking Water Rules and Permit; by July 1, 2017 submit Phase II Technical Review items #2, 5, 8, 12 and 13 on the form entitled "Georgia EPD Water System Review & Permitting Process"; w/in 30 days notify all water customers in writing the Respondent is now working on upgrading the Water System and expansion will be fully permitted no later than July 1, 2017 |
Settlement Amount | $5,000.00 |
Legal Authority | Safe Drinking Water Act |
Date Executed | 23‑Jun‑2017 |
Publication Date For Executed Order | 3‑Jul‑2017 |
File Attachments | None |