Skip to main content

Enforcement Order EPD-WP-8294

Facility Made in the Shade Campground
County Burke County
Cause of Order Operate a Public Water System without first being issued a modified permit from the Division; failure to operate the Water System in accordance with the Rules, Regulations and Orders
Requirements of Order Immediately begin to comply w/ the Drinking Water Act, Drinking Water Rules and Permit; by July 1, 2017 submit Phase II Technical Review items #2, 5, 8, 12 and 13 on the form entitled "Georgia EPD Water System Review & Permitting Process"; w/in 30 days notify all water customers in writing the Respondent is now working on upgrading the Water System and expansion will be fully permitted no later than July 1, 2017
Settlement Amount $5,000.00
Legal Authority Safe Drinking Water Act
Date Executed 23‑Jun‑2017
Publication Date For Executed Order 3‑Jul‑2017
File Attachments None