Enforcement Order EPD-WP-8450

Facility City of Louisville (Louisville Municipal Airport- Runway Safety Area Improvements project)
County Jefferson County
Cause of Order Failed to obtain General Permit coverage for the construction activities
Requirements of Order Fully comply with Act, Rules and associated Permits on any future projects involving land disturbing activities; w/in 7 days provide a copy of the design professional 7 day inspection letter confirming the instillation of the initial sediment storage and perimeter control BMPs; w/in 7 days provide all the daily, weekly, and monthly inspection reports since commencement of construction; conduct storm water turbidity monitoring at designated monitoring locations for a rain event that reaches or exceeds 0.5 inches
Settlement Amount $7,000.00
Legal Authority Water Quality Control Act (including Surface Water Allocation)
Date Executed 21‑Mar‑2018
Publication Date For Executed Order 26‑Mar‑2018
File Attachments None