Requirements of Order |
Achieve compliance with the Total Residual Chlorine (TRC) limitation specified in Part I.B of the permit in accordance with the following schedule: monitor for TRC at the effluent as a grab sample once a month, w/in 6 months submit a design development report (DDR) for modifications needed at the facility that will allow it to meet the TRC limit, w/in 12 months submit plans and specifications for any modifications needed that will allow it to meet the TRC limit, w/in 18 months begin construction of any modifications needed at the facility, w/in 24 months attain compliance with the TRC limitation |