Enforcement Order EPD-AQC-6904
Facility | Mondelez Global LLC |
---|---|
County | Fulton County |
Cause of Order | Violated Condition 4.4 of the Permit by not operating RTO1 above the temperature established during the most recent destruction efficiency test; violation of Condition 2.6 of the Permit by not operating RTO1 at a temperature to maintain the combined capture and destruction efficiency at no less than 90 percent at all times |
Requirements of Order | |
Settlement Amount | $7,000.00 |
Legal Authority | Air Quality Act |
Date Executed | 12‑Apr‑2018 |
Publication Date For Executed Order | 16‑Apr‑2018 |