Facility |
Parramore Fertilizer Site and SoGreen Waste Pile Site |
County |
Tift County |
Cause of Order |
Replaces existing Hazardous Site Response Act Consent Order EPD-HSR-003 and enroll both sites into the Voluntary Remediation Program |
Requirements of Order |
Complete hydrogeologic evaluation of the SoGreen site within 12 months of execution; complete delineation of soil contamination at the PFS within 24 months of execution; update the site Conceptual Site Models, evaluate remedial options, and finalize the Voluntary Investigation and Remediation Plans within 30 months of execution; submit the Compliance Status Report for each site within 60 months of execution; submit semiannual progress reports |
Proposed Settlement Amount |
|
Legal Authority |
Voluntary Remediation Program Act |
Publication Date For Proposed Order |
2‑Jul‑2018 |
Date Comment Period Closes |
1‑Aug‑2018 |
File Attachments |
None
|