Facility |
City of Grantville (LAS Pond #1, Colley Street; Pond #2, Pine Street; Pond #3, Meriwether Street; Pond #4, Lone Oak Road) |
County |
Coweta County |
Cause of Order |
The Grantville LAS Pond #1 exceeded the Monthly Average Total Suspended Solids concentration limit during June 2017 and June 2018; the Grantville Pond #2 exceeded the Monthly Average Biochemical Oxygen Demand (5-day) concentration limit during June 2017 and September 2018; the Grantville Pond #2 exceeded the Weekly Average Biochemical Oxygen Demand (5-day) concentration limit during June 2017 and February 2018; the Grantville Pond #2 exceeded the Weekly Average Flow (MGD) limit established by the Permit during September 2017, October 2017, November 2017 and February 2018; the Grantville Pond #3 exceeded the Weekly Average Biochemical Oxygen Demand (5-day) concentration limit during November 2017 and February 2018,; the Grantville Pond #3 exceeded the Monthly Average Biochemical Oxygen Demand (5-day) concentration limit during April 2018; the Grantville Pond #3 exceeded he Weekly Average Biochemical Oxygen Demand concentration limit during April 2018 and August 2018; the Grantville Pond #3 exceeded the Weekly Average Flow (MGD)limit during August 2018,; the Grantville Pond #4 exceeded the Weekly Average Biochemical Oxygen Demand (5-day) concentration limit during June 2017, February 2018; the Grantville Pond #4 exceeded the Monthly Average Biochemical Oxygen Demand (5-day) concentration limit during July 2018; the Grantville Pond #4 exceeded the Weekly Average Biochemical Oxygen Demand (5-day) concentration limit during July 2018 |
Requirements of Order |
W/in 30 days of execution date of this Consent Order, submit for EPD review and concurrence, a Corrective Action Plan prepared by a licensed professional to assess and address the compliance problems with the Facilities; if the Respondent implements the approved CAP, then any expenditures made directly by the Respondent towards completing the CAP may be used to offset, in partial or full, the stipulated penalty; comply with all effluent limitations established by the Permit |
Settlement Amount |
$13,287.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
23‑Jan‑2019 |
Publication Date For Executed Order |
28‑Jan‑2019 |
File Attachments |
None
|