Facility |
Erosion Control Remediation |
County |
Fulton County |
Cause of Order |
Failed to obtain coverage under the Permit; failed to design, install and maintain an ESPCP; failed to have an ESPCP approved prior to land disturbance activity; failed to install initial BMPs prior to initiation of land disturbance; failed to properly design, install, and maintain BMPs; significant amounts of sediment discharged into state waters; failed to obtain a warm water stream buffer variance |
Requirements of Order |
Obtain all necessary permits from US Army Corps of Engineers prior to any construction activity; install and maintain all erosion and sedimentation control measures; submit a Corrective Action Plan; pay penalty |
Settlement Amount |
$35,000.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
8‑Nov‑2019 |
Publication Date For Executed Order |
11‑Nov‑2019 |
File Attachments |
None
|