Enforcement Order EPD-WP-8836

Facility Dalton Utilities
County Whitfield County
Cause of Order Failure to submit a permit application package
Requirements of Order 1) provide verification of signed contract with an Engineer of Record 2) by August 1, 2020 submit a complete permit application 3) within 180 days of the division issuing a permit, but not prior to December 1, 2020, commence rehabilitation of of the dam 4) within 24 months of issuance of permit, complete the rehabilitation of the dam
Settlement Amount $0.00
Legal Authority Safe Dams Act
Publication Date For Proposed Order 27‑Jan‑2020
Date Comment Period Closes 26‑Feb‑2020
Date Executed 16‑Apr‑2020
Publication Date For Executed Order 20‑Apr‑2020
File Attachments None