Facility |
City of Wrightsville WPCP |
County |
Johnson County |
Cause of Order |
Failed to gain compliance with Order 8437 - the construction of a new wastewater treatment plant and moving the discharge location, completing an inflow & infiltration study and repair work, installing a baffle curtain and chlorination |
Requirements of Order |
Fully complete all necessary construction for the new wastewater treatment facility and ensure all wastewater is directed to the new facility and its new outfall - if respondent fails to do so, they shall be required to pay $2,000 |
Settlement Amount |
$0.00 |
Legal Authority |
Water Quality Control Act (including Surface Water Allocation) |
Date Executed |
15‑Apr‑2020 |
Publication Date For Executed Order |
20‑Apr‑2020 |
File Attachments |
None
|