Enforcement Order EPD-WP-8963

Facility Hiers Lake Dam
County Brooks County
Cause of Order Failed to submit a complete application to operate a dam in accordance with the timeframe; failed to develop and submit an Emergency Action Plan
Requirements of Order Drained lake level must be maintained until Dam is brought into compliance; complete the controlled breach of the Dam with design plans and specification approved by EPD and submit the as-built plans and Engineer of Record's certification that the breach was completed in accordance with design plans
Settlement Amount $0.00
Legal Authority Safe Dams Act
Date Executed 5‑Aug‑2020
Publication Date For Executed Order 10‑Aug‑2020
File Attachments None