Facility |
Rocio Woody |
County |
Fannin County |
Cause of Order |
Conducted land disturbance within the 50 foot buffer without first obtaining a buffer variance, failed to design, install, and/or maintain proper BMPs |
Requirements of Order |
Immediately stop land disturbing activity work on the Site with the exception of installation and maintenance of temporary or permanent erosion and sediment controls, no additions or structural changes that would result in encroachment into the buffer may be made to the existing structures, mitigate for the construction of the 2 structures remaining in the buffer and submit a Corrective Action Plan |
Settlement Amount |
$2,700.00 |
Legal Authority |
Erosion and Sedimentation Act |
Date Executed |
7‑Apr‑2021 |
Publication Date For Executed Order |
12‑Apr‑2021 |