Enforcement Order EPD-WP-9062

Facility Rocio Woody
County Fannin County
Cause of Order Conducted land disturbance within the 50 foot buffer without first obtaining a buffer variance, failed to design, install, and/or maintain proper BMPs
Requirements of Order Immediately stop land disturbing activity work on the Site with the exception of installation and maintenance of temporary or permanent erosion and sediment controls, no additions or structural changes that would result in encroachment into the buffer may be made to the existing structures, mitigate for the construction of the 2 structures remaining in the buffer and submit a Corrective Action Plan
Settlement Amount $2,700.00
Legal Authority Erosion and Sedimentation Act
Date Executed 7‑Apr‑2021
Publication Date For Executed Order 12‑Apr‑2021
File Attachments None