Enforcement Order EPD-AQC-7080
Facility | Savannah Marine Terminal |
---|---|
County | Chatham County |
Cause of Order | Failure to obtain an operating permit for the Savannah Facilities and the Guyton Facility; failure to submit an application for an operating permit within 30 days of commencement of normal operations; failure to pay to EPD an annual fee for calendar years 2017 through 2019; failure to submit a complete Part 70 Permit application within 12 months after commencing operation |
Requirements of Order | Submit a complete Part 70 Permit Application for the operations at the Savannah Facilities; Costs shall be submitted for all control devices and equipment necessary to meet Air Toxic Guidelines; Submit a complete Permit Application for the operations at the Guyton Facility; Complete the online fee reporting form for calendar years 2017 through 2019 and submit payments; submit payment for the 2020 Permit Fees |
Settlement Amount | $22,701.00 |
Legal Authority | Air Quality Act |
Date Executed | 3‑May‑2021 |
Publication Date For Executed Order | 10‑May‑2021 |
File Attachments | None |