Date of Posting: Monday, September 18, 2017

Enforcement Order EPD-WP-8351

Facility ASI Southeast
County Stephens County
Cause of Order Sediment in state waters due to failure to implement and maintain Best Management Practices; failure to collect water samples and perform soil test
Requirements of Order Correct immediately
Settlement Amount $2,500.00
Legal Authority Water Quality Control Act (including Surface Water Allocation)
Date Executed 9/15/2017

Enforcement Order EPD-SW-2781

Facility Folsom Construction Company Inert Landfill
County Crisp County
Cause of Order Failure to cease waste receipt by December 1, 2014 deadline; accepting non-inert wastes inclusive of metals, plastic products, and household litter and by allowing the ponding of storm water on the disposal area
Requirements of Order Immediately cease receipt of waste at the Facility; w/in 45 days remove and properly dispose of all non-inert waste at the Facility to a municipal solid waste landfill; w/in 60 days submit documentation of proper disposal of non-inert waste from the Facility; w/in 90 days complete closure of the Facility
Settlement Amount $2,250.00
Legal Authority Comprehensive Solid Waste Management Act
Date Executed 9/14/2017

Enforcement Order EPD-SM-2775

Facility Browns' Borrow Pit
County Catoosa County
Cause of Order Mining through buffer zones and beyond permit boundary
Requirements of Order Submit an Amendment form and Surface Mining Land Use Plan & provide reclamation plan w/in 180 days; initiate reclamation and complete w/in 2 years
Settlement Amount $2,750.00
Legal Authority Surface Mining Act
Date Executed 9/8/2017